`BRIEF REGARDING “CONSTRUCTION OF HIGH RISE FLATS FOR GOVT. SERVANTS AT PHASE-V HAYATABAD, PESHAWAR”
(Actual Commencement):
1.13 Actual date of completion: January, 2017
1.14 Date of completion: October, 2019
Due to termination of previous consultant / hiring of new consultant / change of design and non-availability of funds the project has been delayed. The new consultant M/S Allied Engineering was hired on 25 jan 2018
The project was approved by PDWP in its meeting held on 11/11/2013 at a cost of Rs. 1115.126 Million. The project envisaged on the construction of 140 No’s of High Rise Flats (HRF) for Government servants at Phase-V Hayatabad, Peshawar. The new consultant was hired on 25 Jan 2019.